CLM Construction undertook the installation of an Impressed Current Cathodic Protection (ICCP) system to the deck soffit between supporting bents underneath Spaghetti Junction of the M6.
AkzoNobel’s Intercrete concrete repair materials were used to complete the 2018 Concrete Spalling Remediation Programme at Hinkley Point B Power Station.